Project Title

Moxy Hotel and Residence Inn

Location

Cork, Ireland

Size

153 Rooms and 41 Long-stay Suites

Update Scope

Full Electrical Services

Delivery of electrical services for a fast-tracked, dual-brand hotel development completed within a constrained city-centre environment.

Overview

The Moxy Hotel and Residence Inn Cork is a €40 million dual-brand hospitality development located on Camden Quay, on the former McKenzies Circuit Courthouse site in the heart of Cork city.

The seven-storey building accommodates two Marriott brands operating under one roof, comprising 153 Moxy hotel rooms alongside 41 long-stay suites branded as Residence Inn, providing a mix of short-stay and extended-stay accommodation.

Despite the challenges associated with a dense urban setting, the project was successfully delivered in just 22 months, marking Update Group’s fourth completed project with JMK Group and a further milestone in its ongoing relationship with Marriott International.

Read More

Our Scope

Update Group was appointed by Marriott International to deliver the full electrical services for the development, supporting both hotel brands and all shared back-of-house and operational areas.

The city-centre location required detailed planning and coordination to manage interfaces with surrounding residential and commercial properties, as well as busy public streets, while maintaining programme certainty and safety.

Close collaboration with the client, contractor and wider project team was critical to sequencing works efficiently, enabling the electrical installation to progress smoothly within a tight construction programme.

Read More

 

Delivering complex electrical services for a dual-brand hotel within a highly constrained city-centre site.

Specifications

Development value:

Approximately €40 million

Building type:

Dual-brand hotel development

Accommodation:

153 Moxy hotel rooms and 41 Residence Inn long-stay suites

Building scale:

Seven-storey city-centre structure

Programme:

Completed in 22 months from start to finish